U.S. Embassy, Manila

Project Details

Walker Construction has a consultant contract with Makati Development for site operations on the New Office Complex at two sitesproject value is $128 million this represents phase one.

Delays and possible LD’s were eliminated by settlement of a REA which was worth $5 million cash and extended completion date till March 2013. Phase 2 is completing ahead of schedule and ready for final inspections by December 2012.

A part of our responsibility were change orders, claims, BIM review, shop drawings, LEED and commissioning.